Lester B. Pearson Catholic School
Original Building Information 1974-2010

April 4, 2011

First Day of Demolition March 28th, 2011 Day 4 of Demolition March 31st
Demolition Date: March 2011
Move Out Date: December 20th, 2010
Move In Date: September 1974
Architects: Stafford & Haensli
General Contractor: Napev Construction
Site: Size - 8.001 acres
Cost - $96,012.00
Building: Area - 28,000 sq. ft.
Cost - $633,770.00
Cost per sq. ft. - $22.63
Furniture & Equipment - $39,700.00